● The project life-cycle can be described as(72). (72)
● The project life-cycle can be described as(72).
(72)
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
正確答案:A試題(72)分析 關(guān)于項(xiàng)目周期劃分正確的是 (72) 。 A.啟動(dòng)、計(jì)劃、執(zhí)行、收尾 B.計(jì)劃、授權(quán)、報(bào)告 C.計(jì)劃、控制、方案設(shè)計(jì)、WBS的發(fā)展、終止 D.啟動(dòng)、執(zhí)行、報(bào)告參考答案 ?。?2)A